KURNIA, SEKAR MAULINA (2023) ANALISIS PENJADWALAN PROYEK DENGAN METODE CPM PADA RUMAH SUSUN PONPES ABU MANSHUR PLERED - CIREBON. S1 thesis, Universitas Mercu Buana Bekasi.
|
Text
41119310056 - Sekar Maulina Kurnia - 01 Cover.pdf Download (794kB) | Preview |
|
|
Text
41119310056 - Sekar Maulina Kurnia - 02 Abstrak.pdf Download (201kB) | Preview |
|
Text
41119310056 - Sekar Maulina Kurnia - 03 BAB 1.pdf Restricted to Registered users only Download (163kB) |
||
Text
41119310056 - Sekar Maulina Kurnia - 04 BAB 2.pdf Restricted to Registered users only Download (496kB) |
||
Text
41119310056 - Sekar Maulina Kurnia - 05 BAB 3.pdf Restricted to Registered users only Download (381kB) |
||
Text
41119310056 - Sekar Maulina Kurnia - 06 BAB 4.pdf Restricted to Registered users only Download (341kB) |
||
Text
41119310056 - Sekar Maulina Kurnia - 07 BAB 5.pdf Restricted to Registered users only Download (132kB) |
||
Text
41119310056 - Sekar Maulina Kurnia - 08 Daftar Pustaka.pdf Restricted to Registered users only Download (170kB) |
||
Text
41119310056 - Sekar Maulina Kurnia - 09 Lampiran.pdf Restricted to Registered users only Download (2MB) |
Abstract
Proyek Pembangunan Rumah Susun Pondok Pesantren Abu Manshur memiliki luas 19,440 m2, dalam pelaksanaanya proyek Rumah Susun ini direncanakan selama 150 hari atau 25 minggu. Dalam pelaksanaan proyek Pembangunan Rumah Susun Pondok Pesantren Abu Manshur terjadi keterlambatan, hal ini dikarenakan keputusan yang lambat, kurangnya koordinasi dan material yang terlambat. Beberapa hal tersebut yang mengakibatkan terjadinya keterlambatan dalam pelaksanaanya. Penelitian ini dilakukan menggunakan Critical Path Method (CPM) yang bertujuan untuk menganalisis durasi waktu yang dibutuhkan dalam menyelesaikan pekerjaan dan juga mengetahui pekerjaan kritis yang dapat mengakibatkan keterlambatan pada proyek tersebut. Penulis melakukan analisis dengan melakukan pengamatan dilapangan dan juga menggunakan Critical Path Method (CPM) guna untuk mengetahui durasi waktu yang dibutuhkan dalam menyelesaikan proyek tersebut. Analisis dan pengolahan data dengan metode CPM dilakukan dengan cara manual dan dengan menggunakan software Microsoft Project. Hasil dari penelitian ini dengan perhitungan menggunakan Critical Path Method (CPM) didapat durasi sebanyak 24 minggu, durasi ini lebih awal seminggu dari durasi awal proyek yang ditargetkan selama 25 minggu. Solusi agar tidak terjadi keterlambatan proyek adalah dengan dilakukannya penambahan tenaga kerja dan jam kerja. Kata Kunci : penjadwalan, durasi, keterlambatan, Critical Path Method (CPM) The Abu Manshur Islamic Boarding School Flats Construction Project has an area of 19,440 m2, in its implementation the Flats project is planned for 150 days or 25 weeks. In the implementation of the Abu Manshur Islamic Boarding School Flats Construction project there was a delay, this was due to slow decisions, lack of coordination and late materials. Some of these things resulted in delays in implementation. This research was conducted using the Critical Path Method (CPM) which aims to analyze the duration of time required to complete the work and also find out the critical work that can cause delays in the project. The author analyzes by making field observations and also uses the Critical Path Method (CPM) to determine the duration of time required to complete the project. Data analysis and processing with the CPM method is done manually and by using Microsoft Project software. The results of this study with calculations using the Critical Path Method (CPM) obtained a duration of 24 weeks, this duration is a week earlier than the initial project duration targeted for 25 weeks. The solution to avoid project delays is to increase labor and working hours. Keywords: scheduling, duration, delays, Critical Path Method (CPM)
Item Type: | Thesis (S1) |
---|---|
Call Number CD: | FT/SIP 23 001 |
NIM/NIDN Creators: | 41119310056 |
Uncontrolled Keywords: | penjadwalan, durasi, keterlambatan, Critical Path Method (CPM) |
Subjects: | 600 Technology/Teknologi > 620 Engineering and Applied Operations/Ilmu Teknik dan operasi Terapan > 624 Civil Engineering/Teknik Sipil |
Divisions: | Fakultas Teknik > Teknik Sipil |
Depositing User: | siti maisyaroh |
Date Deposited: | 04 Jan 2024 08:04 |
Last Modified: | 04 Jan 2024 08:04 |
URI: | http://repository.mercubuana.ac.id/id/eprint/85151 |