RIMAWAN, FAHMIZAN (2019) ANALISIS BIAYA DAN WAKTU PERCEPATAN PEKERJAAN TANAH DENGAN METODE PENAMBAHAN JUMLAH ALAT BERAT PADA PROYEK JALAN TOL DEPOK – ANTASARI. S1 thesis, Universitas Mercu Buana Bekasi.
|
Text
1. Halaman Judul.pdf Download (104kB) | Preview |
|
|
Text
2. Abstrak.pdf Download (181kB) | Preview |
|
|
Text
3. Surat Pernyataan.pdf Download (536kB) | Preview |
|
|
Text
4. Lembar Pengesahan.pdf Download (47kB) | Preview |
|
|
Text
5. Kata Pengantar.pdf Download (130kB) | Preview |
|
|
Text
6. Daftar Isi.pdf Download (171kB) | Preview |
|
|
Text
7. Daftar Tabel.pdf Download (162kB) | Preview |
|
|
Text
8. Daftar Gambar.pdf Download (161kB) | Preview |
|
|
Text
9. Daftar Lampiran.pdf Download (115kB) | Preview |
|
Text
10. Bab 1.pdf Restricted to Registered users only Download (693kB) |
||
Text
11. Bab 2.pdf Restricted to Registered users only Download (1MB) |
||
Text
12. Bab 3.pdf Restricted to Registered users only Download (426kB) |
||
Text
13. Bab 4.pdf Restricted to Registered users only Download (1MB) |
||
Text
14. Bab 5.pdf Restricted to Registered users only Download (202kB) |
||
Text
15. Daftar Pustaka.pdf Restricted to Registered users only Download (186kB) |
||
Text
16. Lampiran.pdf Restricted to Registered users only Download (1MB) |
Abstract
ABSTRAK Judul : Analisis Biaya dan Waktu Percepatan Pekerjaan Tanah Dengan Metode Penambahan Jumlah Alat Berat Pada Proyek Jalan Tol Depok - Antasari, Nama : Fahmizan Rimawan, Nim : 41118310023, Dosen Pembimbing : Irriene Indah Susanti, ST, MT, 2019 Proyek pembangunan Jalan Tol Depok – Antasari mengalami keterlambatan pekerjaan pada pelaksanaan pekerjaan tanah sebesar 30,70% dari presentasi rencana awal Sehingga waktu yang awalnya direncanakan selesai pada bulan Agustus 2019 diperpanjang menjadi harus selesai pada bulan Desember 2019. Dalam Penelitian ini akan menganalisis percepatan durasi penyelesaian pada proyek pembangunan Jalan Tol Depok – Antasari dengan alternatif penambahan jumlah alat berat. Tujuan dari penelitian ini adalah untuk mengetahui biaya proyek yang efisien dan durasi waktu yang lebih cepat dengan menggunakan alternatif tersebut. Hasil analisis pada penelitian ini didapatkan bahwa total biaya proyek dalam kondisi normal ialah sebesar Rp. 9.860.552.249,00 dengan durasi pelaksanaan proyek 130 hari kerja. Dalam kondisi sesudah dipercepat dengan penambahan jumlah alat berat Alternatif – 1 didapat biaya sebesar Rp. 10.030.638.486,00 atau lebih mahal 1,02% dari biaya proyek pada kondisi normal dan durasi pelaksanaan proyek 109 hari kerja atau lebih cepat 21 hari dari durasi normal. Sedangkan total biaya proyek pada kondisi alternatif – 2 didapat sebesar Rp. 10.153.918.103,00 atau lebih mahal 1,04% dari biaya proyek pada kondisi normal dan durasi pelaksanaan proyek 104 hari atau lebih cepat 26 hari dari durasi normal. Dapat diambil kesimpulan bahwa percepatan pekerjaan dengan metode alternatif - 1 merupakan alternatif percepatan yang lebih efektif dan ekonomis, karena dengan menerapkan percepatan alternatif – 1 durasi pekerjaan proyek lebih cepat dari keadaan normal dan tidak mengalami keterlambatan pekerjaan dari waktu rencana yaitu 120 hari. Dan total anggaran biaya proyek lebih murah jika dibandingkan dengan metode percepatan alternatif – 2. Kata Kunci : Percepatan Proyek, Waktu dan Biaya, Penambahan Jumlah Alat Berat ABSTRACT Title : Cost and Time Analysis of the Acceleration of Earthworks with the Method of Adding Heavy Equipment to the Depok - Antasari Toll Road Project, Name : Fahmizan Rimawan, NIM : 41118310023, Advisor : Irriene Indah susanti, ST, MT, 2019 The development of Depok- Antasari Toll road construction was delayed by the work on the implementation of land work of 30.70% from the original plan presentation so that The initially planned time was completed in August 2019 extended to be completed in December 2019. In this study will analyze the acceleration of completion duration on The construction project of Depok – Antasari Toll road with an alternative to the number of heavy equipment. The purpose of this research is to know the cost of project that is physical and duration of time is faster by using the alternative. The results of the analysis was obtained that total project cost under normal conditions is IDR. 9,860,552,249.00 with the duration of project execution 130 working days. In the condition after accelerated with the addition of the number of heavy equipment alternative – 1 obtained a fee of Rp. 10,030,638,486.00 or more expensive 1.02% of the project cost in normal conditions and duration Project execution of 109 business days or faster 21 days from the normal duration. While the total cost of the project in the alternative condition – 2 obtained Rp. 10,153,918,103.00 or more expensive 1.04% of the project cost under normal conditions and duration of project execution 104 days or faster 26 days from the normal duration. It can concluded that the acceleration of work by alternative method-1 is a more effective and economical acceleration alternative, because By applying an alternate acceleration – 1 The duration of project work is faster than normal circumstances and does not experience a delay of employment from the planned time of 120 days. And the total budget cost of the project is cheaper compared to the alternative acceleration method – 2. Keywords : Project Acceleration, Time and Cost, Addition of the number of heavy equipment
Item Type: | Thesis (S1) |
---|---|
Call Number CD: | FT/SIP 19 012 |
NIM/NIDN Creators: | 41118310023 |
Uncontrolled Keywords: | Kata Kunci : Percepatan Proyek, Waktu dan Biaya, Penambahan Jumlah Alat Berat |
Subjects: | 600 Technology/Teknologi > 620 Engineering and Applied Operations/Ilmu Teknik dan operasi Terapan > 624 Civil Engineering/Teknik Sipil |
Divisions: | Fakultas Teknik > Teknik Sipil |
Depositing User: | siti maisyaroh |
Date Deposited: | 09 Mar 2022 08:29 |
Last Modified: | 09 Mar 2022 08:29 |
URI: | http://repository.mercubuana.ac.id/id/eprint/57661 |
Actions (login required)
View Item |