ANALISIS PENGARUH IMPLEMENTASI FOTOGRAMETRI, KOORDINASI INTERNAL DAN KEBIJAKAN EKSTERNAL TERHADAP KINERJA WAKTU MONTHLY CERTIFICATE BERDASAR KEPUTUSAN MANAJER PROYEK PEKERJAAN TANAH JALAN TOL

SETIAWAN, RISKY (2026) ANALISIS PENGARUH IMPLEMENTASI FOTOGRAMETRI, KOORDINASI INTERNAL DAN KEBIJAKAN EKSTERNAL TERHADAP KINERJA WAKTU MONTHLY CERTIFICATE BERDASAR KEPUTUSAN MANAJER PROYEK PEKERJAAN TANAH JALAN TOL. S2 thesis, Universitas Mercu Buana Jakarta.

[img]
Preview
Text (Hal Cover)
COVER.pdf

Download (793kB) | Preview
[img] Text (Bab 1)
BAB 1.pdf
Restricted to Registered users only

Download (389kB)
[img] Text (Bab 2)
BAB 2.pdf
Restricted to Registered users only

Download (482kB)
[img] Text (Bab 3)
BAB 3.pdf
Restricted to Registered users only

Download (658kB)
[img] Text (BAB 4)
BAB 4.pdf
Restricted to Registered users only

Download (1MB)
[img] Text (Bab 5)
BAB 5.pdf
Restricted to Registered users only

Download (155kB)
[img] Text (Daftar Pustaka)
DAFTAR PUSTAKA.pdf
Restricted to Registered users only

Download (271kB)
[img] Text (Lampiran)
LAMPIRAN.pdf
Restricted to Registered users only

Download (1MB)

Abstract

Keterlambatan dalam proses pengajuan dan penerbitan Monthly Certificate (MC) pada pekerjaan tanah proyek jalan tol sering terjadi akibat lambatnya pengambilan keputusan manajer proyek, yang berdampak krusial pada stabilitas arus kas kontraktor. Penelitian ini bertujuan untuk menganalisis secara komprehensif pengaruh implementasi teknologi fotogrametri, koordinasi internal, dan kebijakan eksternal terhadap efektivitas pengambilan keputusan manajer proyek, serta implikasinya terhadap percepatan kinerja waktu MC. Metode penelitian menggunakan pendekatan kuantitatif melalui analisis regresi dan survei kuesioner kepada 49 responden profesional di proyek Jalan Tol Jakarta-Cikampek II Selatan, Akses Patimban, dan Probolinggo-Banyuwangi. Hasil analisis statistik menunjukkan bahwa ketiga variabel independen secara simultan berpengaruh positif dan signifikan terhadap keputusan manajer proyek. Kebijakan eksternal teridentifikasi sebagai faktor paling dominan yang mempengaruhi keputusan manajer proyek. Selanjutnya, kualitas keputusan manajer proyek terbukti memiliki dampak positif yang sangat kuat terhadap kinerja waktu Monthly Certificate. Selain analisis statistik, validasi teknis di lapangan mengungkapkan bahwa teknologi fotogrametri mampu memangkas waktu akuisisi data hingga lebih dari 95% dibandingkan metode konvensional. Namun, ditemukan adanya deviasi akurasi volume pada area tertentu jika dibandingkan dengan Total Station. Delays in the submission and issuance process of the Monthly Certificate (MC) in toll road earthwork projects frequently occur due to slow decision-making by project managers, which has a crucial impact on the contractor's cash flow stability. This research aims to comprehensively analyze the influence of photogrammetry technology implementation, internal coordination, and external policies on the effectiveness of project manager decision-making, as well as its implications for accelerating MC time performance.The research method employs a quantitative approach through regression analysis and questionnaire surveys distributed to 49 professional respondents at the Jakarta-Cikampek II Selatan, Patimban Access, and Probolinggo-Banyuwangi toll road projects. Statistical results indicate that the three independent variables simultaneously have a positive and significant effect on project manager decisions. External policy was identified as the most dominant factor influencing project manager decisions. Furthermore, the quality of project manager decisions is proven to have a very strong positive impact on Monthly Certificate time performance.In addition to the statistical analysis, technical validation in the field reveals that photogrammetry technology is capable of reducing data acquisition time by more than 95% compared to conventional methods. However, volume accuracy deviations were found in certain areas when compared to the Total Station method.

Item Type: Thesis (S2)
NIM/NIDN Creators: 55723120023
Uncontrolled Keywords: fotogrametri, koordinasi internal, kebijakan eksternal, keputusan manajer proyek, monthly certificate
Subjects: 600 Technology/Teknologi > 620 Engineering and Applied Operations/Ilmu Teknik dan operasi Terapan > 624 Civil Engineering/Teknik Sipil
600 Technology/Teknologi > 650 Management, Public Relations, Business and Auxiliary Service/Manajemen, Hubungan Masyarakat, Bisnis dan Ilmu yang Berkaitan > 658 General Management/Manajemen Umum > 658.4 Executive Management/Manajemen Eksekutif
Divisions: Pascasarjana > Magister Teknik Sipil
Depositing User: Haqi ar rachma nur
Date Deposited: 02 Apr 2026 03:55
Last Modified: 02 Apr 2026 03:55
URI: http://repository.mercubuana.ac.id/id/eprint/101392