HADI, DEGA SETYAWAN (2020) ANALISIS PERBANDINGAN METODE ERECTION FULLSLAB PRECAST TERHADAP BIAYA DAN WAKTU (Studi Kasus: Proyek Jalan Tol Cibitung Cilincing Seksi 3). S1-Sarjana thesis, Universitas Mercu Buana Jatisampurna.
|
Text
1. HALAMAN JUDUL.pdf Download (53kB) | Preview |
|
|
Text
2. ABSTRAK.pdf Download (30kB) | Preview |
|
|
Text
3. Lembar Pernyataan.pdf Download (69kB) | Preview |
|
|
Text
4. Lembar Pengesahan.pdf Download (78kB) | Preview |
|
|
Text
5. KATA PENGANTAR.pdf Download (30kB) | Preview |
|
|
Text
6. DAFTAR ISI .pdf Download (63kB) | Preview |
|
|
Text
7. DAFTAR TABEL.pdf Download (29kB) | Preview |
|
|
Text
8. DAFTAR GAMBAR.pdf Download (51kB) | Preview |
|
|
Text
9. DAFTAR LAMPIRAN.pdf Download (23kB) | Preview |
|
|
Text
10. BAB I.pdf Download (314kB) | Preview |
|
|
Text
11. BAB II.pdf Download (448kB) | Preview |
|
|
Text
12. BAB III.pdf Download (305kB) | Preview |
|
|
Text
13. BAB IV.pdf Download (565kB) | Preview |
|
|
Text
14. BAB V.pdf Download (32kB) | Preview |
|
|
Text
15. DAFTAR PUSTAKA.pdf Download (77kB) | Preview |
|
|
Text
16. LAMPIRAN.pdf Download (310kB) | Preview |
Abstract
ABSTRAK Pemerintah Indonesia menggencarkan proyek Infrastruktur di negara ini untuk pemerataan logistik dan pemerataan ekonomi, Infrastruktur tersebut berupa Jalan Tol. Penelitian ini bertujuan untuk menganalisis serta membandingkan biaya, waktu dan metode tepat dalam pekerjaan erection Fullslab Precast pada 1 Modul. Data yang digunakan adalah data primer dan sekunder. Menggunakan metode pengangkatan/erection dengan alat berat Crane. Untuk perhitungan analisis perbandingan didapatkan dengan analisis biaya dan analisis waktu. Pengamatan dilapangan, serta perhitungan analisis biaya langsung dan tidak lansung menjadi perhitungan yang akan dimuat agar mendapat metode yang tepat terhadap Biaya dan waktu pekerjaan. Hasil metode yang tepat adalah metode 1 Crawler Crane dengan biaya Rp 206.598.086,00 dan Waktu 12 hari terhadap pekerjaan karena Crawler Crane dapat mengangkat Fullslab Precast dari stockyard Kata Kunci: Analisis, Fullslab Precast, Metode, Biaya, Waktu. ABSTRACT The Government of Indonesia is intensifying Infrastructure projects in this country for logistical and economic equality, the infrastructure is in the form of Toll Roads. This study aims to analyze and compare costs, time and exact methods in the Fullslab Precast erection work on 1 Module. The data used are primary and secondary. Using the method of lifting / erection with heavy equipment Crane. For comparative analysis calculations obtained by cost analysis and time analysis. Field observations, with direct cost and nondirect cost analysis calculations are calculated to be loaded in order to get the right method for the Cost and time of work. The results of right methode as 1 Crawler Crane with a cost of Rp 206.598.086,00 and 12 days time to work because the Crawler Crane can lift Fullslab Precast from the stockyard Keywords: Analysis, Fullslab Precast, Method, Cost, Time.
Item Type: | Thesis (S1-Sarjana) |
---|---|
Call Number CD: | FT/SIP 20 038 |
NIM: | 41118310110 |
Uncontrolled Keywords: | Analisis, Fullslab Precast, Metode, Biaya, Waktu. |
Subjects: | 600 Technology/Teknologi > 620 Engineering and Applied Operations/Ilmu Teknik dan operasi Terapan > 624 Civil Engineering/Teknik Sipil |
Divisions: | Fakultas Teknik > Teknik Sipil |
Depositing User: | Nasruddin Mansyur S.Hum |
Date Deposited: | 25 Sep 2020 08:28 |
Last Modified: | 25 Sep 2020 08:28 |
URI: | http://repository.mercubuana.ac.id/id/eprint/57316 |
Actions (login required)
![]() |
View Item |