RUDYPRATAMA, BILLY (2021) ANALISIS PERGERAKAN UPLIFT TANAH YANG MENYEBABKAN KERUSAKAN PIPA FIREFIGHTING PADA AREA HEAT RECOVERY STEAM GENERATOR (HRSG) BLOK 4.3 PROYEK ADD-ON PLTGU MUARA TAWAR BEKASI. S1 thesis, Universitas Mercu Buana Jakarta.
|
Text (HAL COVER)
01 Cover.pdf Download (537kB) | Preview |
|
![]() |
Text (BAB I)
02 BAB 1.pdf Restricted to Registered users only Download (251kB) |
|
![]() |
Text (BAB II)
03 BAB 2.pdf Restricted to Registered users only Download (1MB) |
|
![]() |
Text (BAB III)
04 BAB 3.pdf Restricted to Registered users only Download (407kB) |
|
![]() |
Text (BAB IV)
05 BAB 4.pdf Restricted to Registered users only Download (1MB) |
|
![]() |
Text (BAB V)
06 BAB 5.pdf Restricted to Registered users only Download (164kB) |
|
![]() |
Text (DAFTAR PUSTAKA)
07 Daftar Pustaka.pdf Restricted to Registered users only Download (60kB) |
|
![]() |
Text (LAMPIRAN)
08 Lampiran.pdf Restricted to Registered users only Download (14MB) |
Abstract
The Muara Tawar PLTGU Add-On Combine Cycle Power Plant (CCPP) project is divided into three major areas, namely, Head Recovery Steam Generator (HRSG), Steam Turbine Generator (STG), and Balance of Plant (BOP). The area that the authors review focuses on is civil works in the HRSG area. Civil works in the HRSG area are divided into two major parts, namely the lower structure and the upper structure. The lower structural work consists of pile foundations, pile cap, and pedestal. While the upper structure consists of steel structure installation work. The discussion limitation in this final project is the foundation work of HRSG Block 4.3. During the project, there was a problem that occurred in the HRSG area related to civil works. An existing building in the form of a curved firefighting pipe is thought to be due to project activities in the HRSG Block 4.3 area. There are several possible causes for the pipe to buckle. The curve that occurs in the pipe results in the pipe not functioning for some time. Any project activity should not disturb the stability and function of the existing building even though the damage is very small. The entire work implementation must be considered from a technical and non-technical point of view so as not to damage the surrounding buildings. To avoid a similar incident, it is necessary to analyze the causes of damage to the firefighting pipe in the HRSG Block 4.3 area. The discussion will be carried out by looking for lateral and vertical deformation values using numerical methods in Plaxis 2D software and using empirical formulas. The results of the analysis are in the form of lateral and vertical deformations that occur in the soil due to piling, as well as finding alternative solutions to reduce the impact of damage. Key words: Sub-structure, firefighting pipe damage, piling Proyek Combine Cycle Power Plant (CCPP) Add-On PLTGU Muara Tawar terbagi atas tiga area besar yaitu, Head Recovery Steam Generator (HRSG), Steam Turbine Generator (STG), serta Balance of Plant (BOP). Area yang menjadi fokus tinjauan penulis adalah pekerjaan sipil di area HRSG. Pekerjaan sipil pada area HRSG terbagi atas dua bagian besar, yaitu struktur bawah dan struktur atas. Pekerjaan struktur bawah terdiri dari pondasi tiang pancang, pile cap, hingga pedestal. Sedangkan pada struktur atas terdiri dari pekerjaan instalasi struktur baja. Batasan pembahasan pada tugas akhir ini adalah pekerjaan pondasi HRSG Blok 4.3. Selama proyek berlangsung terdapat sebuah permasalahan yang terjadi di area HRSG berkaitan dengan pekerjaan sipil. Sebuah bangunan eksisting berupa pipa firefighting melengkung diduga akibat aktivitas proyek di area HRSG Blok 4.3. Ada beberapa kemungkinan penyebab yang menyebabkan pipa tersebut melengkung. Lengkung yang terjadi pada pipa mengakibatkan pipa tersebut tidak berfungsi selama beberapa waktu. Aktivitas proyek apapun seharusnya tidak mengganggu stabilitas dan fungsi bangunan eksisting walaupun kerusakan yang timbul sangat kecil. Seluruh pelaksanaan pekerjaan harus diperhatikan dari segi teknis maupun non teknisnya agar tidak merusak bangunan sekitar. Untuk menghindari kejadian serupa, maka perlu dilakukan analisis penyebab kerusakan pada pipa firefighting di area HRSG Blok 4.3. Pembahasan akan dilakukan dengan mencari nilai deformasi lateral dan vertikal dengan menggunakan metode numerik pada perangkat lunak Plaxis 2D dan menggunakan rumus empiris. Hasil analisis berupa deformasi lateral dan vertikal yang terjadi pada tanah akibat pemancangan, serta dicari solusi alternatif untuk mengurangi dampak kerusakan. Kata kunci: Struktur bawah, kerusakan pipa firefighting, pemancangan
Actions (login required)
![]() |
View Item |