WIDIYATMOKO, GINANJAR (2018) ANALISIS PEMBERSIHAN SUDU KOMPRESOR TURBIN GAS UNIT 2.1 PADA PLTG BLOK 2 UNIT PEMBANGKITAN MUARA KARANG. S1 thesis, Universitas Mercu Buana Jakarta.
|
Text (HAL COVER)
01. Halaman Judul.pdf Download (22kB) | Preview |
|
|
Text (ABSTRAK)
02. Abstrak.pdf Download (55kB) | Preview |
|
|
Text (LEMBAR PERNYATAAN)
03. Surat Pernyataan.pdf Download (41kB) | Preview |
|
|
Text (LEMBAR PENGESAHAN)
04. Lembar Pengesahan.pdf Download (745kB) | Preview |
|
|
Text (KATA PENGANTAR)
05. Kata Pengantar.pdf Download (66kB) | Preview |
|
|
Text (DAFTAR ISI)
06. Daftar Isi.pdf Download (32kB) | Preview |
|
|
Text (DAFTAR TABEL)
08. Daftar Tabel.pdf Download (20kB) | Preview |
|
|
Text (DAFTAR GAMBAR)
07. Daftar Gambar.pdf Download (26kB) | Preview |
|
|
Text (DAFTAR NOTASI)
09. Daftar Notasi.pdf Download (122kB) | Preview |
|
Text (BAB I)
10. BAB I.pdf Restricted to Registered users only Download (101kB) |
||
Text (BAB II)
11. BAB II.pdf Restricted to Registered users only Download (982kB) |
||
Text (BAB III)
12. BAB III.pdf Restricted to Registered users only Download (298kB) |
||
Text (BAB IV)
13. BAB IV.pdf Restricted to Registered users only Download (482kB) |
||
Text (BAB V)
14. BAB V.pdf Restricted to Registered users only Download (94kB) |
||
Text (DAFTAR PUSTAKA)
15. Daftar Pustaka.pdf Restricted to Registered users only Download (97kB) |
||
Text (LAMPIRAN)
16. Lampiran.pdf Restricted to Registered users only Download (997kB) |
Abstract
PLTG is a power plant that utilizes gas as a working fluid. In the Gas Turbine the kinetic energy is converted into mechanical energy in the from of rotation that drives the turbine wheel so as to produce power. PLTG often has maximum load (Base Load). So, PT PLN through P2B (Load Control Centre) will be requesting the PLTG’s primary generator to increase production of electricity reaching up to maximum load resembling DMN (Power Net Capacity) as agreed upon the contract performance or based on the real capacity of the generator. It often occurs reduction of power generated by PLTGU. This generator isn't capable to gain the agreed DMN, so often comes down derating. Decrease in the performance of this plant can be affected because the value of compressor efficiency decreases below 90 % at full load. To overcome these problem, Compressor Blade Washing is needed to clean up the dust and dirt that are attached to compressor blade so the compressor outlet temperature down and pressure rise so that compressor, so as to increase compressor efficiency value above 90 % at full load. Compressor Blade Washing process is performed when the Gas Turbine does’n operated. The research method used in this study is quantitative research method. The result this study indicated, after Compressor Blade Washing process occur decrease compressor outlet temperature 10,2 °C, increase in compressor pressure 28.000 Pa, and increas the compressor efficiency 2,93 % at full load. Keywords: Gas Turbine, efficiency, Compressor Blade Washing PLTG merupakan suatu pembangkit listrik yang memanfaatkan gas sebagai fluida kerja. Di dalam turbin gas energi kinetik dikonversikan menjadi energi mekanik berupa putaran yang menggerakkan roda turbin sehingga menghasilkan daya. PLTG sering mengalami beban maksimum (Base Load). Sehingga pihak PT PLN melalui P2B (Pusat Pengaturan Beban) akan meminta pembangkit yang terutama PLTG untuk menaikkan produksi listrik mencapai beban maksimal sesuai dengan DMN ( Daya Mampu Netto ) yang telah di setujui melalui kontrak kinerja atau kemampuan aktual dari pembangkit tersebut. Sering terjadi penurunan daya yang dihasilkan oleh PLTG. Pembangkit ini tidak mampu memenuhi DMN yang telah di setujui, sehingga akan terjadi derating. Penurunan performa pembangkit ini dapat dipengaruhi karena nilai efisiensi kompresor yang semakin menurun dibawah 90 % pada saat beban penuh. Untuk mengatasi permasalahan tersebut, maka perlu dilakukan proses Pembersihan Sudu Kompresor yang bertujuan untuk membersihkan debu dan kotoran yang melekat pada sudu kompresor agar temperatur outlet kompresor turun dan tekanan kompresor naik, sehingga dapat meningkatkan nilai efisiensi kompresor diatas 90 % pada saat beban penuh. Proses Pembersihan Sudu Kompresor dilakukan pada saat gas turbin tidak beroperasi. Metode penelitian yang digunakan dalam penelitian ini yaitu metode penelitian kuantitatif. Hasil penelitian ini menunjukkan bahwa, setelah dilakukanya proses Pembersihan Sudu Kompresor ada penurunan temperatur outlet kompresor 10,2 °C, kenaikan tekanan kompresor 28.000 Pa, dan kenaikan efisiensi kompresor sebesar 2,93 % pada saat beban penuh. Kata Kunci: Turbin Gas, efisiensi, Pembersihan Sudu Kompresor